  1. Weekly Progress Report
    2/28 – 3/6
    Group: S2
    Report #: 5
    Date: 3/6/09

    Meetings
    This week our team met once on Tuesday during the class period. Since we put a lot of work into our project in the prior week this meeting was used specifically to polish our narrative. This meeting ran smoothly and at the close of the meeting slide responsibilities were delegated.

    Status of Old/Current Tasks:
    This week we completed our narrative, schedule, and takeoff.

    Upcoming Tasks:
    On Monday when we return from break we will rehearse our presentation in preparation for Tuesday’s presentation.
    Issues/ Group Problems
    Upon review of Dr. Fiori’s temperament analysis our group is working to try to expand our creative thought and not become stagnant with our work and presentation.

    Site Visit Observations:
    No site visits were taken this week.

    ReplyDelete
  2. Weekly Progress Report
    2/28-3/6
    Group: J2
    Report #: 4
    Date: 3/6/09

    Meetings
    Team J2 met on Monday morning to review that status of the assignment and tie up any loose ends. We also met on Tuesday afternoon to format and finalize our report. Work has also been getting done on an individual basis.

    Status of Old/Current Tasks:
    Assignment 2 has been completed and turned in to the M-groups.

    Upcoming Tasks:
    Team J2 is prepared to present their completed assignment 2 on Tuesday,March 17th. After the presentation, we plan on beginning preliminary work on Assignment 3.

    Issues/ Group Problems
    The team managed to get the work completed and the report put together on time. There were no problems faced during this hectic work submittal period.

    Site Visit Observations:
    No site visits were taken by the group this week.